Reading a duct and beam clash in plan and section
A line crossing a beam on plan is a question, not proof of a clash. The duct may pass below it, run beside it or meet it at the same elevation. A section through the crossing turns a crowded ceiling drawing into a decision that can be checked.

Use one elevation datum
In a worked example, the beam underside is 2,900 mm above finished floor and the ceiling is at 2,550 mm. The gross vertical gap is 350 mm. A duct with an external insulated depth of 320 mm leaves 30 mm before support and installation allowances. Those 30 mm are a remainder, not acceptance.
Test the route against both trades
Mark the light fitting, sprinkler pipe or cable tray that also uses the same void. Moving the duct sideways may preserve the ceiling height but create a new conflict further along. Compare an alternative section at the next crossing before the design team chooses a route.
What should the revised drawing show?
Add the section marker, datum, external duct dimensions and agreed installation zone to the plan. Keep the earlier revision available so the workshop can identify affected pieces. A coordinated route is useful only when fabrication and installation receive the same change.
Reading the clearance illustration
Move the depth slider below until the remainder reaches zero. At that point the illustrated duct consumes the entire gross opening. A negative remainder means the two drawn envelopes overlap. Even a positive remainder still needs checking against real brackets, insulation details and the installation sequence. This is why a section with explicit dimensions is more useful to a workshop than a coloured clash marker without a height reference.